concrete8 min read

How Much Concrete Do I Need for a Garage Base?

A garage base needs more concrete than a shed base - and more care. Get the thickness, mix and quantity right with this step-by-step guide.

Related calculators

A friend of mine laid his own garage base a couple of years ago. He was meticulous about the sub-base - hired a plate compactor, compacted in two layers, checked his levels with a long straight edge. But when it came to the concrete itself, he ran short. He had calculated for 100mm depth and ordered accordingly, but when the ready-mix arrived and was poured, the finished depth came out at 80-85mm. He had not accounted for the fact that the sub-base level was not quite as consistent as he thought, creating low spots that needed more concrete.

The slab is fine - 85mm is not a disaster - but he tells the story to illustrate why adding a generous wastage allowance to a garage base pour is not optional.

This guide covers everything you need to get the quantity right.

Why ready-mix is almost always the answer

For a shed base you might genuinely debate between bags and ready-mix. For a garage base, that debate is usually over quickly.

A single garage base at 150mm depth is around 2.25 m3 of concrete. At a typical bag yield of 0.012 m3 per 25kg bag, that is approximately 190 bags - and that is before wastage. Mixing 190 bags by hand would take the better part of a day with a hired mixer. It would also produce inconsistent concrete as the mix changes slightly with each batch.

Ready-mix arrives already mixed to a consistent specification, is pumped or chuted directly to where you need it, and the whole pour is done in an hour. At volumes above about 1 m3, ready-mix is almost always the right choice on cost and practicality combined.

The formula

Volume (m3) = Length (m) x Width (m) x Thickness (m)

If thickness is in mm, divide by 1000 first.

Single garage example

Garage 5m x 3m, 150mm thick:

  • Volume = 5 x 3 x 0.15 = 2.25 m3
  • Add 10% wastage = 2.475 m3
  • Round up to nearest 0.25 m3 = 2.5 m3 to order

Double garage example

Garage 6m x 6m, 150mm thick:

  • Volume = 6 x 6 x 0.15 = 5.4 m3
  • Add 10% wastage = 5.94 m3
  • Round up = 6.0 m3 to order

For your exact dimensions, use the Concrete Base Calculator.

How thick should a garage base be?

UseMinimumRecommended
Standard cars, domestic use100mm125-150mm
Heavy SUV or people carriers125mm150mm
Occasional van / light commercial125mm150mm
Workshop, heavy equipment150mm175mm
Regular heavy vehicle use175mmSeek advice

For most domestic garages used by family cars, 150mm is the right target. It is thick enough to handle ordinary vehicle loads, tolerates minor sub-base inconsistencies better than 100mm, and is not prohibitively more expensive than a thinner slab.

Volumes by common garage size

GarageAreaVolume at 100mmVolume at 150mm
Single (4.8m x 2.7m)13m21.3 m31.95 m3
Single (5m x 3m)15m21.5 m32.25 m3
Single (5m x 5m)25m22.5 m33.75 m3
Double (6m x 6m)36m23.6 m35.4 m3
Double (6m x 7m)42m24.2 m36.3 m3
Double (7m x 7m)49m24.9 m37.35 m3

Add 10% wastage and round up to nearest 0.25 m3 for your actual order.

Sub-base: the most important part

Before any concrete goes in, you need a proper sub-base. This is where the long-term performance of your garage floor is determined.

A typical garage floor build-up from bottom to top:

  1. Subgrade (natural ground, well compacted)
  2. Geotextile membrane (recommended, especially on clay)
  3. 150-200mm compacted MOT Type 1 sub-base
  4. DPM (1000 gauge polythene, lapped up the sides)
  5. Concrete slab 100-150mm

Total excavation depth: approximately 300-400mm below finished floor level.

Use the MOT Type 1 Calculator to work out sub-base quantities before you plan the concrete pour.

What concrete mix to use

For a garage base, ask for a minimum C25 (GEN4/ST4) concrete. C25 gives good strength and reasonable abrasion resistance for a floor surface.

If you want better long-term floor durability - particularly if you will be parking on it permanently and doing workshop work - C30 is worth the small extra cost per m3. It is more resistant to abrasion and freeze-thaw cycles.

Do not use C15 or C20 for a garage floor.

Do I need reinforcement mesh?

For a standard domestic car garage, steel mesh is not strictly required and is not universally specified.

However, it is worth considering if:

  • Your sub-base quality is uncertain
  • The slab spans more than 3-4m without a joint
  • Heavy vehicles will use the garage regularly
  • You want added insurance against cracking

If you use mesh, A142 fabric (6mm bars at 200mm centres) is the standard domestic spec. Use plastic spacer chairs to hold it mid-depth - not laying it on the ground before pouring.

My tips for a garage base pour

Having poured a few concrete bases and watched several more being done, here is the honest practical advice:

Book the ready-mix supplier early and have a contingency plan. Ready-mix suppliers have minimum orders and surcharges for small loads. Call at least a week in advance, confirm the volume, and be honest about the access (can they get a full-size truck to your site, or do you need a smaller truck or a pump?). Have a rough number for a second smaller order in case the pour runs slightly short.

Pour and level the same day. Unlike bags where you can stop and start, a ready-mix delivery needs to be poured, spread and roughly levelled before the driver needs to leave (typically 1-2 hours from batch). Have two people minimum.

Hire a concrete vibrating poker. Air pockets in a concrete slab are weak spots. A concrete vibrating poker (available from hire centres) pushes air bubbles to the surface. Run it slowly through the slab as you pour - it takes five minutes and significantly improves the finished strength.

Cure the slab properly. Cover with plastic sheeting or damp hessian for at least 3 days, ideally 7. In hot weather, this is critical - concrete that dries too fast in the sun is weaker and more prone to surface cracking.

Do not drive on it for 7 days. Initial set takes 24-48 hours. Full working strength takes 28 days. A week without vehicles is a reasonable minimum.

Get your volume confirmed with the Concrete Base Calculator before calling the supplier.

Frequently asked questions

Planning estimates only

These results are estimates for planning purposes only. Actual material quantities can vary based on site conditions, compaction, wastage, product size, installation method and supplier guidance. For structural, safety-critical or regulated work, always consult a qualified professional.

Back to all guides