flooring6 min read

Self-Levelling Compound vs Floor Screed: Which One?

Both level floors but they are not the same product, the same process, or the same cost. Here is the honest comparison so you can choose correctly.

When someone tells me their floor is uneven and they are not sure whether to use self-levelling compound or screed, the first question I ask is: how uneven, and what is there now?

Those two answers almost always tell you which product to use. Not because the products are complicated, but because they solve different problems at different scales.

A floor that is 3mm out of flat across 20m2 needs SLC. A floor being constructed from bare structural concrete needs screed. The confusion usually comes when the two problems exist on the same site - and they often do.

What each product is for

Self-levelling compound (SLC) is a finishing product. It flows under gravity to create a flat surface. It is designed for thin applications - typically 2-20mm depending on the product. It is quick, clean to apply, and relatively expensive per kg compared to screed materials.

Floor screed is a construction product. It builds depth, levels a rough slab, encapsulates underfloor heating, and provides a structural base for floor coverings. It works at 25-75mm depth. It is slower to apply, more labour-intensive, much cheaper per m3, and needs significantly longer to dry.

Head-to-head comparison

FactorSelf-levelling compoundFloor screed
Typical depth2-20mm25-75mm
ApplicationPoured and rakedMixed and laid manually
LabourLow - pours itselfHigher - manual laying and screeding
Drying time1-24 hours to walk onDays to weeks
Cost per m2 at typical depthHigherLower
Suitable over UFH pipesNoYes
Can go over existing floorYes (with primer)No - structural application only
Minimum depth2-3mm25mm (bonded)

When to use self-levelling compound

  • Existing concrete or screed floor that is basically sound but uneven
  • Renovation project preparing an existing floor for tiling
  • New build where the structural slab is flat but not perfectly level
  • Thin correction layer (under 15mm) before a floor covering
  • Quick turnaround needed - most SLC products allow tiling within 24 hours

When to use floor screed

  • New build or extension floor construction from scratch
  • Covering underfloor heating pipes
  • Raising floor level significantly (over 20mm)
  • Floating floor over insulation boards
  • When cost per m2 matters - screed is substantially cheaper than SLC at depth

When you need both

This is more common than people realise. A new extension might have a structural concrete slab that is well constructed but has minor irregularities. The contractor lays sand:cement screed to the correct depth and with the correct falls. Once cured, they apply a thin layer of SLC to achieve the perfectly flat, smooth finish that modern large-format tiles require.

The screed does the heavy lifting - building depth, covering the insulation and UFH pipes, providing the structural floor. The SLC does the fine work - creating the flatness tolerance that a rigid tile adhesive and large format tile demand.

Cost comparison

Costs vary by region and supplier, but as a rough guide per m2 of finished floor:

MethodMaterial cost per m2 (approx)
SLC at 5mm£3-6
SLC at 10mm£6-12
Sand:cement screed at 50mm£2-4 (materials only)
Anhydrite liquid screed at 65mm£8-15 (pumped)

SLC is approximately 3-5x the material cost of sand:cement screed per unit volume. This matters on large floors - for a 30m2 floor needing 50mm of build-up, SLC would cost around £150-400 in materials where screed would cost £60-120. The economics of using SLC for depth correction quickly become unworkable.

My tips on choosing

Check the existing floor condition first. If the floor has hollow areas, cracks or significant structural problems, no surface product will fix that. The base needs sorting before either screed or SLC is applied.

Do not use SLC as a cheap shortcut. Some people pour SLC thick to avoid a proper screed on a new build. At depth, SLC is more expensive than screed and not designed for the structural role screed performs. It will be thinner in some areas, cracking is possible, and costs are higher.

Test moisture before applying SLC to old screed. An existing floor that appears dry may have high residual moisture that will cause adhesion failure with SLC or the floor covering above it. A basic calcium carbide test or RH probe will tell you if the floor is ready.

For tiling over either product, the floor needs to be flat to within 3mm under a 3m straight edge for standard tiles, and closer to 2mm for large-format tiles. If existing screed is within those tolerances, you may not need SLC at all.

Use the Self-Levelling Compound Calculator or Floor Screed Calculator for your specific project.

Frequently asked questions

Planning estimates only

These results are estimates for planning purposes only. Actual material quantities can vary based on site conditions, compaction, wastage, product size, installation method and supplier guidance. For structural, safety-critical or regulated work, always consult a qualified professional.

Back to all guides